EHS Helps Repair Critical Bridge on DC's National Mall


In its first foray into the nation's Capital, on the weekend of April 16th, EHS was happy to assist the Federal Highway Administration on a project on the National Mall, to upgrade the bridge deck overlay of Independence Avenue over Maine Avenue.

EHS divided the project into three shifts and had 40 of its employees staff the project, 24/7 over the course of the weekend.


The work included micromilling to remove the existing overlay and replacing it with a Kwikbond Polyester Polymer Concrete Overlay. This project was unique in that the National Parks has requested a "dark gray" color for the overlay which is traditionally more of a tan color. Working with Kwikbond we were able to provide a pigmented product that satiisfied the aesthetic need of the project.